S.N.G.N. ROMGAZ S.A. - SNG

Addendum to NIP Financing Contract - CTE Iernut

Release Date: 7/8/2021 9:32:46 AM

IRIS Code: ADDB3

CURRENT REPORT

In compliance with Law no. 24/2017 regarding Issuers of Financial Instruments

 

Report date: July 8, 2021

Company name: Societatea Nationala de Gaze Naturale ROMGAZ S.A.

Address: Medias, 4 Constantin I. Motas Square, Sibiu County – Romania, 551130

Phone/fax no: 004-0374-401020 / 004-0269-846901

Fiscal Code: RO14056826

LEI Code: 2549009R7KJ38D9RW354

Trade Register registration number: J32/392/2001

Subscribed and paid in share capital: 385,422,400 RON

Regulated market where the issued securities are traded: Bucharest Stock Exchange (BVB), London Stock Exchange (LSE)

 

 

Significant event to be reported:

 

·         Addendum concluded to the Financing Contract no. 4/ December 7, 2017 for the investment "Combined cycle CCTG power plant" - Iernut

 

 

Government Decision no. 669/2021 amended Government Decision 1096/2013 for approving transitional free allocation of CO2 certificates to electricity producers during 2013-2020, including the National Investment Plan (NIP). Government Decision no. 669/2021 extends: the completion and commissioning period of investments financed from the NIP until June 30, 2022, the reimbursement period until December 31, 2022 and the other correlative periods.

 

Consequently, on July 7, 2021, was sent by the Ministry of Energy the Addendum no.5 to the Financing Contract no. 4/ December 7, 2017 for the investment "Combined cycle CCTG power plant" – Iernut, signed by both parties. The object of the Addendum is the modification of the contract term until December 31, 2022, for financing, as well as the modification of the investment schedule, provided in the contract.

 

We recall that the conclusion of the the Financing Contract no. 4/ December 7, 2017 for the investment "Combined cycle CCTG power plant" – Iernut was the object of the Current Report published on December 11, 2017.

 

 

Chief Executive Officer,

Aristotel Marius JUDE

 

 



 Print

Information provided by IRIS, the news platform of the Bucharest Stock Exchange.

______________________

Bucharest Stock Exchange ("BVB") is not responsible for the content of this News item. Issuers whose financial instruments are traded on markets operated by BVB are required to report in accordance with current legal and regulatory provisions. BVB publishes these Reports as market administrator, appointed by ASF. When, for investors’ information, Reports are published, either signed by different persons, or with conflicting information, legal liability lies fully with the signatories. BVB disclaims any obligation or responsibility towards issuers or third parties, regarding the reality, completeness and accuracy of information provided by them and distributed by BVB. Website users are responsible for checking content. Any news item (including any prospectus) which is addressed solely to the persons and countries specified therein should not be relied upon other than by such persons and/or outside the specified countries. Terms and conditions, including restrictions on use and distribution apply.


©2016 Bucharest Stock Exchange. All rights reserved